The first project of the 2024 season was the supply and installation of a domestic wastewater treatment plant for a permanently occupied holiday home in the picturesque valley of the River Lužnice. The model chosen was the BC 4 PP OPTIMA.
The client previously had a cesspit with a usable volume of 8.0 m³ on the plot. In recent years, however, the cost of emptying it had risen dramatically: having 1.0 m³ of wastewater removed from the tank cost CZK 1,600.
Replacing the cesspit with a modern domestic WWTP is expected to pay for itself in less than 1 year, which is excellent.
The WWTP tank was placed in the space of the former holding tank, which made the project logistically more demanding. So that the client could get back to normal use once the original cesspit had been taken out of service, the whole system had to be replaced within a few days. In this case the outlet from the WWTP discharges directly into the River Lužnice. The blower and the OPTIMA control unit are housed in the adjacent workshop.