The project included excavation work, positioning of the treatment plant, joining up the pipework and complete hook-up to the sewer connection. Thanks to well-coordinated work, the installation went ahead without complications.

Domestic wastewater treatment plants08 / 2025
Project photo: Installation and commissioning of a domestic WWTP BC 4 OPTIMA, Suchdol nad Lužnicí View the images
Project photo

THE PROJECT IN A NUTSHELL

A specific place.
A specific solution.

Solution area
Domestic wastewater treatment plants
Project period
08 / 2025
Technology
BioCleaner BC 4 OPTIMA
Scope of work
Turnkey supply including excavation, installation of the WWTP, pipework and commissioning.

HOW IT WENT

From the brief
to the finished solution.

Read the full story of the project, the technology used and the individual steps.

Original reference
Prefer to talk it all through in person?+420 736 403 795
01In August 2025 we completed another turnkey job, this time in Suchdol nad Lužnicí.
In August 2025 we completed another turnkey job, this time in Suchdol nad Lužnicí. For a family house we supplied and commissioned a BioCleaner BC 4 OPTIMA in the polypropylene (PP) version.

The project included excavation work, positioning of the treatment plant, joining up the pipework and complete hook-up to the sewer connection. Thanks to well-coordinated work, the installation went ahead without complications.

The customer has thus gained a modern, environmentally friendly and reliable wastewater treatment solution that will provide convenient operation with minimal maintenance costs.