If the installation instructions from the wastewater treatment plant manufacturer are not followed, problems can arise that a DIY builder cannot solve alone. We were contacted by the owner of a new BC 4 BASIC plant, who had bought it from…

Service call-outsDomestic wastewater treatment plants03 / 2025
Project photo: Domestic WWTP Dynín View the images
Project photo

THE PROJECT IN A NUTSHELL

A specific place.
A specific solution.

Solution area
Service call-outs / Domestic wastewater treatment plants
Project period
03 / 2025
Technology
BC 4 BASIC
Scope of work
Repair of a tank deformed by incorrect installation and refitting of the internal technology.

HOW IT WENT

From the brief
to the finished solution.

Read the full story of the project, the technology used and the individual steps.

Original reference
Prefer to talk it all through in person?+420 736 403 795
01If the installation instructions from the wastewater treatment plant manufacturer are not followed, problems can arise that a DIY builder…

If the installation instructions from the wastewater treatment plant manufacturer are not followed, problems can arise that a DIY builder cannot solve alone. We were contacted by the owner of a new BC 4 BASIC plant, who had bought it from an unnamed online shop, without installation or commissioning.

This is how problems often start. Without the necessary knowledge and experience, a poorly executed installation can cause irreversible damage to the tank and losses running into tens of thousands of Czech crowns.

In this case the customer did not follow the installation instructions and backfilled around a plastic tank that had not been filled with water. Within a short time the pressure of the surrounding soil deformed the tank, twisted the baffle walls, disconnected the outlet pipe and made the final settling tank “pop out” of its original position.

02We carefully removed all the internal technology from the WWTP tank.

We carefully removed all the internal technology from the WWTP tank. We dug partly around the tank to reduce the external pressure on its walls. We then tried filling the tank with water, which pushed the deformed walls back into their original position. Once the tank had been straightened, we refitted the internal technology in its original place.

Fortunately, with the BioCleaner BC WWTP the manufacturer has thought this issue through, so a great many installation mistakes can be put right. And this was one of them.

The treatment plant is now as good as new and is awaiting its official start-up and final building approval.

NOW IT'S YOUR PROJECT'S TURN

A similar situation?
We'll find your way forward.

Tell us a little about the site and what you have in mind. We'll discuss the next steps together.