Installing the technology isn't enough. It also has to work properly.
Once the refurbishment was complete, we tested the individual process functions one by one.
We checked the aeration of the activation section, the pumping, the skimming of floating debris, the aeration of the final settling section, the control system, the running of the blower and the operating cycles as set. Once the functional tests were complete, the WWTP was put back into operation.
But our work doesn't end there.
After the refurbishment of the mechanical and process parts, the next important step is to restore the biological process. To get it started faster, seeding the activation section with activated sludge from a working municipal WWTP was recommended, followed by monitoring of how the biological process develops.